Design Engineering changes to increase throughput on a 36” Crown Hoe litho press system, which typically was limited to 63 passes per minute. Upon completion the line was capable of speeds up to 85 passes per minute |
|
Designed Quick Change system utilizing adhesive backed measuring tape to dial in pre-set adjustments. |
|
Crown Hoe 36” Upgrade Modification |
|
Lean Automation of Case Erector |
|
Projects underway and completed |


|
PET Blow Molding Change time reduced from 12.5 hours down to 2 hours 11 minutes in two sessions. |
|
SMED Implementation Shows 84% improvement in C/O Downtime |
Typical SMED Results from Organized SystemsPACKAGING SMEAD TEAMTHE ROAD TO SET-UP REDUCTIONFACILITATE TEAM MEETINGSTRACK CHANGEOVER TIMESIMPLEMENT NEW SET-UP PROCEDURESIMPLEMENT QUICK CHANGE IDEAS SUBMITTED FROM TEAMSET NEW TEAM GOALSOVERSEE CHANGEOVERSRESOURSE TEAMENSURE ALL BOTTLES AND CORRUGATION IS PACKED OUT BEFORE DOWNSTREAM CHANGEOVER BEGINSENSURE STAGING OF NEW CORRUGATION FOR NEXT RUNENSURE PROPER SKID TAGS ARE PROVIDEDSUPPLY SET UP BOTTLES FOR CHANGE TEAM TO SET UP ALPS LEAK DETECTOR AND PEARSON PACKEROVERSEE TOOLING CHANGES DOWNSTREAMPROVIDE PERSONNEL TO BUILD A BOX BANK PRIOR TO START-UPDEBUG DOWNSTREAM BEFORE RELEASE OF 1ST. SHIFT PACKOUT TEAM MEMBERS
SIDEL & PROCESS TEAM LEADERINSPECT MOLDS SETS PRIOR TO CHANGEOVERSPROVIDE CORRECT PROCESS SET-UP SHEETSPROVIDE OVEN CONFIGURATION SET-UP INFORMATIONPROVIDE PROCESS SUPPORTCOORDINATE BOTTLE SPECIFICATIONS POSTINGS WITH QUALITY RESOURCEPRODUCTION SUPERVISORSVERIFY PREFORM SOURCE AND INVENTORIESENSURE PRE-STAGING OF PREFORM FOR NEXT RUNPROVIDE MECHANIC SUPPORT WHEN NEEDEDBMT’S PACKOUT TEAMCOMMUNICATE PRODUCTION SCHEDULE AND CUSTOMER REQUIREMENTS TO TEAMVERIFY CORRUGATE AVAILABILITY AND DELIVERY TIMESPROVIDE PART NUMBER TAGS FOR BOTTLE PRODUCTIONQUALITY SOURCEVerify section weight cutter set upEnsure posting of bottle specifications on lineProvide up to date bottle section weightsProvide data reflecting bottle performance of last run of new productEnsure all new products adhere to GPC-830Facilitate timely hot fillsCHANGEOVER TEAMCONTRIBUTE SET-UP REDUCTION IDEA’S TO THE TEAMRECORD STEP 22 CHANGE OVER TIMESWORK AS TEAM TO REACH SIX HOUR CHANGE OVER GOALCHANGE OVERPRODUCT LINESPROMOTE SAFETYTEAM GOALSUnderstand the benefits for set-up reduction.TEAM GOALS2. Formulate a procedure to analyze the steps taken during a mold change.3. Document times of each step of the mold change.4. Analyze the mold change step times and make recommendations to reduce each part of the process.5. Compile all recommendation and submit to SMEAD team for discussion.6. Format a change-over procedure using new step recommendations.7. Perform change-over using new procedure and compare step times to old procedures for any actual setup reductions.8. Assess the results.9. Present results to team.FIRST STEPVIDEO TAPE THE CHANGE OVERVIEW TAPE AND DOCUMENTORGANIZE INTO STEPSFORMAT INTO WORK SHEETUSE FOR NEXT CHANGEFIRST SET-UP STEP BREAKDOWNPROCESS 29%HOT FILLS 7%PREPARATION 14%LINE CHANGE 49%ASSESS THE RESULTSBRING DATA BACK TO TEAMASSESS THE RESULTSDISCUSS WAYS FOR IMPROVEMENTDOCUMENT SUGGESTIONSIMPLEMENT FOR NEXT PRODUCT CHANGEIMPLEMENTATIONIMPLEMENT 22 STEP WORK SHEET INTO PROCEDURECONTINUAL IMPROVEMENTSET NEW GOALSREWARD ACHIEVEMENTS
Note: 2000 average change over on the SBO-18 /II was 12.36 Hr’s 4-16-2001 After SMED Team implemented, The team was able to reduce the change over average to 2.11 Hr’s This is an astonishing 83 percent improvement. Team members, let’s plan a recognition event for all the members of your respective teams. |